Bend Bulletin - Opal Springs fish ladder opens doors for trout, salmon

This article was published on: 12/2/19 12:00 AM

By Michael Kohn

Just call him Finlay. That’s the name given to the first steelhead to officially climb the newly opened fish ladder at Opal Springs Hydroelectric Project, once a barrier to anadromous fish trying to reach spawning areas in the upper Crooked River.

Finlay — named in honor of the project’s lead consultant, Finlay Anderson — was recorded on a web camera swimming into the current at the final stage of the $11 million ladder and spillway project, according to Joel Gehrett, general manager for the Deschutes Valley Water District, the entity that manages the project.

Finlay struggled momentarily against the current but safely reached the top side of the Opal Springs dam, the first steelhead to get that far on its own in more than 30 years. Other fish, including rainbow trout and whitefish, were also seen making use of the ladder.

The fish ladder project — completed earlier this month after two years of construction — was a long-anticipated milestone for fish making their way through Central Oregon’s network of rivers and streams as part of their life cycle.

Dams, canals and other man-made barriers have threatened numerous fish species in Central Oregon for decades, but the construction of fish ladders like the one at Opal Springs is a key step toward fish recovery efforts.

Before the opening of the ladder, project workers at the site had to manually capture the fish with nets at the bottom of the hydroelectric project and place them back in the river above the dam.

Anderson was humbled upon hearing the news that the first steelhead was named in his honor.

“That’s really cool. I appreciate the gesture, but it’s a testament to the Deschutes Valley Water District who persevered and made it happen. It’s really all about them and it’s a neat story,” Anderson said.

The project is located less than a mile upstream from the Crooked River Arm of Lake Billy Chinook. No ladder was installed when the dam was built in the mid-1980s because at that time natural fish passages were already blocked downstream by the Pelton Round Butte Project.

A $100 million project to improve fish passage and habitat at the Pelton Round Butte Hydroelectric Project improved conditions for fish passage, and adult salmon and steelhead began their return to the Upper Deschutes and Crooked river system.

While some fish made their way up the Deschutes and Metolius rivers, most headed up the Crooked River, according to Brett Hodgson, Deschutes District fish biologist for the Oregon Department of Fish and Wildlife.

Biologists cannot definitively explain why fish prefer the Crooked River route, said Hodgson.

“It could be out-migrating smolts are able to move out of the Crooked more effectively than in the Deschutes/Whychus. Thus, there are more adults to return to the Crooked River,” Hodgson said.

Another reason, Hodgson suggests, is the unusual configuration of Lake Billy Chinook simply allows for easier passage up the Crooked Arm.

When they reached the Opal Springs dam, the Deschutes Valley Water District passed fish above Opal Springs through a trap-and-haul effort. The new ladder allows fish to get through unaided.

Gehrett, head of the water district since August, said the team was challenged by some unexpected boulders that needed to be broken up during the construction of the ladder, but engineering aspects of the project were otherwise uneventful.

“There was great coordination between the owner of the dam and the contractors. Unexpected problems were dealt with really well,” said Gehrett, who left his role as head of utility services in Des Plaines, Illinois, earlier this year in order to manage the water district.

While fish ladders can take various forms, the unit at Opal Springs is a gently ascending, water-filled series of steps that doubles back on itself, with 38 shallow pools along the way that give fish a chance to rest on the upward journey.